Agenda and minutes

Venue: Liverpool Suite. View directions

Contact: Shauna Healey, Democratic Services Manager 

Items
No. Item

1.

Preliminary Matters

Minutes:

Members considered the identification of declarations of interest, any urgent additional items, and any business that may require the exclusion os ght press and public.

 

RESOLVED that:

 

a)    no declarations of interest were made by individual members in relation to any items of business on the agenda;

 

b)    no additional items of business to be considered as matters of urgency were determined by the Chair; and

 

c)     no items of business required the exclusion of the press and public during consideration thereof because of the possibility of the disclosure of exempt information.

2.

Minutes of the Last Meeting pdf icon PDF 61 KB

To consider the minutes of the last meeting hed on 10th February 2022.

Minutes:

RESOLVED that the minutes of the last meeting held on 10th February 2022 were agreed as an accurate record.

 

3.

Grant Thornton 2021/22 Audit Plan pdf icon PDF 70 KB

To consider report CFO/015/22 provided by external auditors, Grant Thornton.

Additional documents:

Minutes:

Georgia Smith presented the Audit Plan for 2021/22, which considered the risksGeorgia Smith presented the Audit Plan for 2021/22, which considered the risks identified as part of their audit work. Members were advised that some of the risk identified were common across local government and the public sector such as evaluations on land and buildings.

 

The report presented the value for money work undertaken and it was confirmed that there were no significant risks to report in that area.

 

Councillor Makinson noted the Authority’s relationship with the district authorities and asked if there was a need to review that risk in relation to electricity contracts, as discussed at the recent Urgency Committee. It was explained that the Authority had three lines of defence starting with the Audit Committee who were charged with scrutinising governance arrangements and procurements. Secondly, Internal Audit were able to provide a plan in relation to emerging risks that could provide the Members with some insight into whether the risk needed to be escalated. Finally, External Audit consider the risks and whether the appropriate level of assurance is provided.

 

The Chief Fire Officer, Phil Garrigan, queried the change in costs for Grant Thornton’s services which had risen by £6,000 from the proposal received in 2021. Georgia Smith explained that extra work had been undertaken on the evaluation of land and buildings and there had been delays as well as issues with the quality of information provided. Extra work was undertaken to provide assurance and these additional costs were being reviewed by PSAA as part of a rigorous challenge process. Ian Cummins added that the level of assurance needed had changed as a result of new demands by the Government which were subsidises with a grant of £15,000 for the additional work. Furthermore, actions had been taken to ensure that the right standard of information would be provided on time in the future.

 

Members queried the financial risk surrounding pension liability which was a common issue in public sector bodies. It was explained that under accounting standards, the Authority worked out the liability in perpetuity based on an underlying assumption which can change year to year. The liability was based on actuarial assumptions in order to account for future liability and as such it was common to see big movements. Ian Cummins noted that this was different to the budget which provided a more accurate view when compared to the Outturn report.

 

With regards to the McCloud case, Member’s were advised that there could potentially be an increase or decrease in liability. For the Fire Pension scheme, the Government was carrying out an actuary review which a report expected in 2024-25 to identify if employer or employee contributions would need to change. This would be taken into consideration in the 2023-24 budget. 

 

RESOLVED that the contents of the report be noted.

 

4.

Grant Thornton Request - Informing the Audit Risk Assessment 2021/22 pdf icon PDF 82 KB

To consider report CFO/016/22 provided by external auditors, Grant Thornton.

Additional documents:

Minutes:

Ian Cummins presented the report which considered the Authority’s response to a questionnaire from external audit on management processes and oversight.

 

Councillor Makinson noted that there had been no cases of fraud and asked if there had been any attempted cases of fraud and if so how they were managed by the Authority. Members were advised that the anti-fraud policy was being reviewed alongside the whistle-blowing policy to be more efficient. If there was any suspected fraud there would be a full investigation and a report back to the Audit Committee, but there had been none to report. 

 

With regards to training, Ria Groves, Monitoring Officer, explained that this was to be delivered this year as well as training on the Gifts and Hospitality Policy.

 

Ian Cummins noted that Internal Audit were also considering the Authority’s Fraud Policies and that work was progressing as expected. Those updated procedures would be brought back to the Authority for consideration as they were expected to change substantially.

 

RESOLVED that:

 

a)    the Director of Finance and Procurement’s responses to the Grant Thornton risk assessment questions outlined in Appendix A be reviewed; and

 

b)    the responses outlined in Appendix A be approved, subject to any Member amendments.

 

5.

Treasury Management 2021/22 Annual Report pdf icon PDF 342 KB

To consider Report CFO/017/22 presenting the Treasury Management Annual Report.

Additional documents:

Minutes:

Members were reminded that they had received regular updated on performance against the Treasury Management Strategy as part of its quarterly reports. The report advised Members on the 2021-22 outturn provision and activities undertaken by the Authority and it was highlighted that Treasury Management performance had been in line with the approved strategy and within the agreed borrowing limits.

 

RESOLVED that the report be noted.

 

6.

The Annual Governance Statement 2021/2022 pdf icon PDF 77 KB

To report CFO/019/22 which provides Members with the Annual Governance Statement for 2021/22.

Additional documents:

Minutes:

The Members considered the Annual General Statement for 2021/22 which provided a review of governance and the systems of internal control in operation throughout the year. 

 

The report outlined the potential risk and challenges to be faced in 2022-23 and Ian Cummins noted that the current position was that the Authority had the financial resilience to meet those challenges.

 

RESOLVED that the 2021/2022 Annual Governance Statement be approved.

 

7.

2022/23 internal audit plan pdf icon PDF 82 KB

Additional documents:

Minutes:

Ian Cummins presented the proposed plan for 2022-23 which suggested audit work to be carried out over the next year. It was explained that the Authority had 112 audit days as part of its service level agreement with Liverpool City Council and 12 audit days had been carried forward into 2022-23 as a result of deferred work.

 

The allocation had been considered by the Strategic Leadership Team with 57 days arranged to cover seven strategy reviews. The balance of days would be apportioned to ad hoc unplanned audit work and audit management.

 

The Chief Fire Officer acknowledged the comments previously made by Councillor Makinson in respect of third party contractual arrangements and the recent Urgency Committee. It was explained that the Authority had considered its utility costs and its arrangements with Liverpool City Council which would be reviewed.

 

Furthermore, it was noted that there was a timescale in the plan for counter fraud policies which would provide Members with reassurance that their concerns were being addressed.

 

RESOLVED that:

 

a)    the proposed audit plan and the areas of focus within be sighted and considered; and

 

b)    the 2022/23 Internal Audit Plan be approved.

 

 

8.

2021/22 Annual Year End Internal Audit Plan pdf icon PDF 89 KB

To consider Report CFO/18/22 presenting the Year End Internal Audit Plan 2021/22.

Additional documents:

Minutes:

Members considered the 2021/22 annual end of year report which provided summaries of the work carried out by Internal Audit. It was noted that Internal Audit had concluded that the Authority provided substantial assurances in accordance with proper practice and that based on their work they were not aware of any significant weaknesses.

 

RESOLVED that the contents of the report be noted.